 |
Thursday,
August 31, 2006 |
This
month's Inside Lines informs PJM's stakeholders of various committee
actions, upcoming training and other activities. PJM would like to highlight
the following:
Department of Energy Releases Congestion Study
Electric
transmission congestion costs millions of dollars annually and threatens
reliability of the grid itself, according to the recently released National
Electric Transmission Congestion Study. The study, done by the federal
Department of Energy, was released during a media briefing in August.
(more)
PJM’s
Summer Performance Sets New Records
This
summer PJM met successive record-setting peak demands for electricity.
The last and highest peak was recorded on Aug. 2, when PJM met a record
for 144,796 megawatts (MW). The previous record was set the day before
at 144,000 MW. (more)
Early
August Demand Response Produces $650 Million Savings
Conservation
during heat waves not only stretches power supplies, it saves money. Reductions
in electricity use during the early August heat wave produced price reductions
estimated to be equivalent to more than $650 million in payments for energy
for the week. (more)
Providing
feedback about PJM.com drives enhancements
During
the past three months, PJM has received many comments through the feedback
form on the PJM Web site. Using that feedback, PJM works continually to
make it easier for users of the Web site to find the information they
need. Among the many enhancements, is the ability to sort the list of
PJM members by name and by sector. This functionality is now available
on the Member
List Web page.
More
improvements are coming, however, members can suggest additional ones
by e-mailing PJM at webfeedback@pjm.com.
|
www.pjm.com
We are unable to respond
to account inquiries sent in reply to this e-mail. To contact us by phone,
please call our member hotline at 610.666.8980 or toll free 866.400.8980.
|
|
What's
Inside:
Committees
Report
Highlights
Regulatory
Reports
|
| Regulatory
Reports |
Committee Updates |
Upcoming Training |
PJM FERC Orders
08.22.2006
ER06-491-001,
ER06-497-001 (PDF)
On August 22, 2006, in Docket Nos. ER06-491 and ER06-497, the Commission
denied Requests for Rehearing from CED Rock Springs, LLC (CED) and
Old Dominion Electric Cooperative (ODEC). The requests were based
on a March 17, 2006 Order in which the Commission rejected the proposed
rate schedules that would have allowed CED and ODEC to recover revenue
requirement for certain costs, from transmission service customers,
incurred in connecting their facilities to the transmission grid.
(more)
|
PJM
FERC Filings
08.28.2006
Docket
No. ER06-1177-000 (PDF)
On August 28, 2006, in Docket No. ER06-177-000, PJM filed an answer
to Indeck-Elwood, LLC's answer to PJM's answer to Indeck-Elwood's
protest of PJM's proposed amendments to Part IV of the PJM Tariff
concerning security requirements and the option to build.
(more) |
|
PJM Reminders
Upcoming stakeholder
meetings can be found on PJM's meeting
advisor. The
next MC meeting will be held on September 28, 2006.
Summaries
of all committee meetings will be provided in this newsletter.
New Members
PJM welcomes the following new members:
- EPCOR
Merchant and Capital (US) Inc.
- North
America Power Partners LLC
- Silverhill
Ltd.
- Duquesne
Conemaugh LLC
- Duquesne
Keystone LLC
- Horizon Wind Energy
LLC
|
|
09.12.2006 PJM
101: The Basics
09.25.2006 – 09.29.2006 Load
Serving Entity 201
10.02.2006
– 10.13.2006 Initial
Training Program
10.17.2006 Generation
101
10.18.2006 Generation
201
10.19.2006 Generation
301
10.20.2006 Operations
101
10.24.2006 – 11.02.2006 Initial
Training Program
|
| Committee
Report |
Committee Meetings:
August
-
Regional
Planning Process Working Group (RPPWG)–
08.31.2006 – Topics: Generation Interconnection Timing, Cost Allocation
for Market Efficiency Projects, Cost allocation for Spare Transformers.
- Planning
Committee (PC)
–
08.30.2006 – Topics: PCLLR Discussion, PJM Hot Weather Performance
Update, *Reactive Limits Manual Language, NERC update, Planning Committee
“Parking Lot”.
-
Market
Settlements Working Group (MSWG)–
08.30.2006 – Topics: FERC EQR Reporting, Marginal Losses Implementation,
Administrative Items.
- Transmission
Expansion Advisory Committee (TEAC)
–
08.30.2006 – Topics: PJM will present its incremental transfer
capability analysis of bulk power transmission alternatives proposed
after the TEAC meeting held in Richmond on July 11.
-
Governance
Working Group (GWG)
– 08.30.2006 – Topics: PJM will present a tutorial on the
use of the eRooms product.
-
Dispatcher
Training Taskforce (DTTF)–
08.29.2006 – Topics: Report from SOS Liaison, eDART, PJM Operations
Training 2006, Seminar Wrap Up, LMS, Upcoming Operator Training, PJM
Drills, Revisions to PJM Operational Manuals, PJM Operator Certification,
NERC Certification.
-
Transmission
Owners Agreement-Administrative Committee (TOA-AC)–
08.24.2006 – Topics: Administrative Items, 500-230kV Transformer
Replacement Strategy, Pandemic Preparedness, PJM RTEP, Legal Issues
Team Update, TOA-AC 2006 Work Plan update, DOE Congestion Study, Finance
Committee Update, NERC TOs' and Operators' Forum, RFC update, Other
Business.
-
Demand
Side Response Working Group (DSRWG)/Metering
Issues Subcommittee (MIS)
Joint Meeting – 08.24.2006 – Topics: Metering Issues Subcommittee
– Review of Team Charter, Review Workshop Results, Metering Data
Options, Options At The Customer Site, Roundtable Discussion of Billing
and Settlement Issues in a “Future” Environment, Building
the Agenda for the Next Meeting. Demand Side Response Working Group
– Demand Side Response Reports, Metering Issues Subcommittee Update,
eLOAD Response Update, Future eLOAD Response Enhancements.
-
Data
Management Working Group (DMWG)–
08.17.2006 – Topics: Roundtable Discussion eDART Method for Submitting
EMS Model Changes, One-Line Diagrams, Presentation on PJM Contingency
Lists Development, ICCP Link Availability Statistics.
-
Nuclear
Generation Owners/Operators User Group (NGOUG)–
08.17.2006
-
180
Day Report (180DRWG)
–
08.16.2006 - Topics: Working Issues List, Action Items.
-
Systems
Information Subcommittee (SIS)
– 08.16.2006 - Topics: Member Company Roundtable, PJM Operations,
Inter-RTO Activities, eSuite Update, PJM Net, Electric Utility Security
Issues, Communication and System Issues, Metrics, eTUG.
-
Operating
Committee (OC)–
08.15.2006 - Topics: Review of Operations, NERC Critical Infrastructure,
System Operations Subcommittee (SOS), Black Start Services, PJM Winter
Reserve Maintenance Scheduling Target, Voltage Schedule Working Group,
Demand Side Response, Markets and Reliability Committee, Market Implementation
Committee, System Information Subcommittee (SIS), Eastern Interconnection
PHASOR PROJECT, Reliability First Update, OC Action Items.
- Regional
Planning Process Working Group (RPPWG)
–
08.11.2006 - Topics: Generator Interconnection Timing, Declining Generation
Profiles, Cost Allocation.
-
Governance
Working Group (GWG)–
08.10.2006 - Topics: Working Group Protocols and Conduct of Meetings,
Protocols for Sector Operations, Sector Definitions and Qualifications
for Membership in Sectors, Alternate Governance Protocols.
- System
Operations Subcommittee (SOS)
–
08.9.2006 - Topics: Review of Operations, eDART User Group Update, System
Operator Certification, Generator Limits and Ramp Rates via ICCP, ICCP
Planned Datalink Outages, Reactive Issues.
-
Finance
Committee (FC)– 08.9.2006 - Topics: Second Quarter
2006 Unaudited Financial Statements, Second Quarter 2006 Quarter Financial
Review, 2006 Forecast, 2007 Preliminary Budget, 2006 – 2010 Financial
Projections, Proposed Tariff Scheduled 9-FINCON, Sector Elected Representative
Requested Status Update.
-
Markets
Implementation Committee (MIC)–
08.8.2006 - Topics: Timing Changes for OASIS (JCM), Transmission Outage
Acceleration Update, FTR Proposal, ARR Allocation Proposal, Loop Flow
Update, Spinning Market Generator Performance, Generator Reactive Testing
Notifications, eMKT User Interface, Demand Side Response Working Group
Update, Black Start Services Working Group Update, Market Settlements
Working Group, 180-Day Stakeholder Process.
-
Members
Committee (MC)– 08.03.2006 - Topics: Consent Agenda,
Market Efficiency In The Regional Transmission Planning Process, Excess
Congestion Revenue, Marginal Losses Allocation, Management Reports,
ERO and ReliabilityFirst, State Activities, Annual Plan, Markets and
Reliability Committee.
-
Markets
& Reliability Committee (MRC)–
08.02.2006 - Topics: Update On Summer Operations, Timing Changes for
OASIS (JCM), Small Generator Interconnection Working Group, Demand Response,
CT Offers In The Day-Ahead Market, Review of Proposed 2007 Projects,
Planning Committee Report.
Return
to Top
|
| Highlights |
| Department
of Energy Releases Congestion Study
Electric transmission congestion
costs millions of dollars annually and threatens reliability of the grid
itself, according to the recently released National Electric Transmission
Congestion Study. The study, done by the federal Department of Energy,
was released during a media briefing in August.
In addition, the growing demand
for power is outpacing the ability to alleviate transmission congestion,
the study said.
Among the most critically congested
areas designated by the DOE study is the Atlantic coastal area from metropolitan
New York to northern Virginia. DOE categorizes congestion into three types:
critical congestion areas, congestion areas of concern and conditional
congestion areas. An area is designated a critical congestion area where
it is "critically important to remedy existing or growing congestion
problems because the current and/or projected effects of the congestion
are severe."
The study did not recommend
national transmission corridors. However, DOE will make the national corridor
designations based on this study’s findings and information from
stakeholders. Designation by DOE would allow the Federal Energy Regulatory
Commission (FERC) backstop authority to approve interstate lines in designated
corridors. Backstop authority enables FERC to act on permitting if states
fail to do so within a year.
PJM was among the first to
seek early designation of two transmission corridors designed to address
congestion problems, which now are identified in the DOE study. PJM’s
two proposed corridors are the Allegheny Mountain Path, extending from
the West Virginia panhandle region southeastward and serving population
in Baltimore and Washington areas, and the Delaware River Path, extending
from West Virginia region eastward and serving population centers around
Philadelphia, New Jersey and Delaware. Congestion costs resulting from
constraints in the Allegheny Mountain path totaled $747 million in 2005,
with another $464 million on the Delaware River path that year.
The study also notes that,
while the eastern portion of PJM experiences continuing load growth, it
is also faces power plant retirements and limited new generation projects.
Transmission constraints are causing significant congestion in both the
western and eastern portions of PJM because the grid cannot accommodate
delivering the available lower-cost Midwest coal- and nuclear-fueled generation
to the East.
The
DOE study was mandated by the Energy Policy Act of 2005. Comments on the
study are due by October 10, 2006. The study recommends PJM as the authority
for transmission planning and further recommends joint studies with the
other northeastern RTOs.
Return
to Top
PJM’s
Summer Performance Sets New Records
This
summer PJM met successive record-setting peak demands for electricity.
The last and highest peak was recorded on Aug. 2, when PJM met a record
for 144,796 megawatts (MW). The previous record was set the day before
at 144,000 MW.
The
difference in peak between last summer’s and this year’s is
more than 10,000 MW—enough electricity to power a large city.
During
the August heat wave, Michael J. Kormos, PJM senior vice president-Reliability
Services said that it was the members’ efforts that enabled PJM
to meet the peak demand over successive days of extreme heat.
“We
continue to witness outstanding performance by transmission system owners,
generators, demand response providers and our system operators,”
Kormos said.
Market-participating
demand response contributed 400 MW of capacity during the peak hour on
Aug. 2. In PJM’s wholesale electricity market, electricity consumers
can be paid the market price for electricity for reducing their use of
electricity. (See related story in this newsletter.)
Requests
for voluntary conservation of electricity requests were called on a few
days this summer because of high temperatures. In addition, utility customers
on interruptible or curtailable rates were told to reduce their electricity
use. These customers receive a special rate or payments from their electric
utilities. The customers agree to eliminate or significantly reduce their
use of electricity when told to do so.
Highest Peak Demands
| Aug. 2, 2006 |
144,796 MW
* |
| Aug. 1, 2006 |
144,000 MW * |
| July 17, 2006 |
139,746 MW * |
| July 26, 2005 |
133,763 MW |
*
These numbers are subject to verification.
Return
to Top
Early
August Demand Response Produces $650 Million Savings
Conservation
during heat waves not only stretches power supplies, it saves money. Reductions
in electricity use during the early August heat wave produced price reductions
estimated to be equivalent to more than $650 million in payments for energy
for the week.
On
Aug. 2, when customers in the PJM region set the new record for power
consumption, voluntary reductions in electricity use, known as demand
response, resulted in price reductions estimated to be equivalent to more
than $230 million in payments for energy.
“These
voluntary curtailments reduced wholesale energy prices by more than $300
per megawatt-hour during the highest usage hours,” said Andrew L.
Ott, PJM vice president - Markets. “While many wholesale customers,
such as utilities, were hedged against high real-time spot-market prices,
all customers will benefit from the dramatic price reductions because
future longer-term electricity sales are based on prices set in the real-time
market, where prices were lower as a result of demand response.”
Demand
response involves reducing the use of electricity (demand) to meet a power
grid need rather than increasing generation (supply). Customers offer
to reduce their usage of electricity in return for being paid the market
value of the electricity saved. Demand response can lower the price of
electricity by avoiding the use of the most expensive generators.
Customers
who curtail their usage receive payments based on the price to generate
an equal amount of electricity. PJM payments to demand response providers
for the heat wave during the first week in August were about $5 million.
“Transmission
owners, generation operators and demand response providers played critical
roles in allowing PJM to provide a record amount of electricity while
maintaining reliable grid operations,” Ott said.
Return
to Top
Providing
feedback about PJM.com drives enhancements
During
the past three months, PJM has received many comments through the feedback
form on the PJM Web site. Using that feedback, PJM works continually to
make it easier for users of the Web site to find the information they
need. Among the many enhancements, is the ability to sort the list of
PJM members by name and by sector. This functionality is now available
on the Member
List Web page.
More
improvements are coming, however, members can suggest additional ones
by e-mailing PJM at webfeedback@pjm.com.
Return
to Top
|
| Regulatory
Reports |
FERC Orders
August
- 08.22.2006
ER06-491-001,
ER06-497-001 (PDF)
On August 22, 2006, in Docket Nos. ER06-491 and ER06-497, the Commission
denied Requests for Rehearing from CED Rock Springs, LLC (CED) and Old
Dominion Electric Cooperative (ODEC). The requests were based on a March
17, 2006 Order in which the Commission rejected the proposed rate schedules
that would have allowed CED and ODEC to recover revenue requirement
for certain costs, from transmission service customers, incurred in
connecting their facilities to the transmission grid.
- 08.18.2006
Docket
Nos. ER06-880-001, ER06-456-004 (PDF)
On August 18, 2006 the Commission issued an order in Docket Nos. ER06-880-001
and ER06-456-004 granting rehearing for further consideration of the
Commission order issued in this proceeding on June 19, 2006.
- 08.16.2006
ER06-1187-000
(PDF)
On August 16, 2006, the Commission issued a letter order accepting PJM's
compliance filing to implement Standards for Business Practices and
Communication Protocols for Public Utilities pursuant to Order No. 676,
effective 7/1/06 under ER06-1187.
- 08.15.2006
ER06-1194-000
(PDF)
On August 15, 2006, The Commission accepted revisions to Attachment
H-13, effective September 1, 2006.
- 08.14.2006 Docket
No. ER06-1218-000 (PDF)
On August 14, 2006, the Commission issued a letter order in Docket No.
ER06-1218-000 directing PJM to file an informational letter describing
how its Long-Term Transmission Rights (LTTRs) correlate to the Long-Term
Transmission Rights Notice of Proposed Rulemaking (NOPR) in Docket No.
RM06-8. The Commission requested a response from PJM within 14 days
of the date of the letter order.
- 08.04.2006
ER06-1146-000
(PDF)
On August 4, 2006, the Commission issued an order accepting for filing
an executed interconnection service agreement among PJM, Brookfield
Power Piney & Deep Creek, LLC, and Pennsylvania Electric Company,
effective May 17, 2006, as requested.
- 08.03.2006
ER06-1144-000
(PDF)
On August 3, 2006, the Commission issued an order accepting for filing
an executed interconnection service agreement among PJM, Brookfield
Power Piney & Deep Creek, LLC, and Pennsylvania Electric Company,
effective May 17, 2006, as requested.
July
- 07.27.2006 ER03-1101-009,
ER03-1101-010 (PDF)
On July 27, 2006, in Docket No. ER03-1101, the Commission issued an
Order on Compliance Filings accepting PJM's third and fourth six-month
reports on the effects of PJM's credit policies on virtual traders which
were required by the Commission's orders issued in this same docket
on September 22, 2003 and December 20, 2004.
- 07.26.2006 Docket
No. ER06-319-003 (PDF)
On July 12, 2006 the Commission issued an order in Docket No. ER06-319-003
granting rehearing for further consideration of the Commission order
issued in this proceeding on May 11, 2006.
Return
to Top
FERC Filings
August
- 08.28.2006
Docket
No. ER06-1177-000 (PDF)
On August 28, 2006, in Docket No. ER06-177-000, PJM filed an answer
to Indeck-Elwood, LLC's answer to PJM's answer to Indeck-Elwood's protest
of PJM's proposed amendments to Part IV of the PJM Tariff concerning
security requirements and the option to build.
- 08.28.2006
Docket No. ER06-1218-000
(PDF)
On August 28, 2006, PJM made an informational compliance filing in Docket
No. ER06-1218-000 in which it describes how PJM's LTTR Proposal correlates
with each of the guidelines as set forth in the Commission's Final Rule
as issued on July 20, 2006.
- 08.25.2006
Docket
No. RM06-12-000 (PDF)
On August 25, 2006, PJM filed comments in the Commission's Notice of
Proposed Rulemaking (NOPR) in Docket No. RM06-12-000. In addition to
offering specific proposals to be considered when adopting the final
rule, PJM offered to work with the Commission in any technical conference
or other procedures initiated in this rulemaking.
- 08.24.2006
EL06-97-000
(PDF)
On August 24, 2006, Midwest ISO and PJM filed a Joint Motion to request
that the Commission grant a ten-day extension of the comment date in
the complaint filed at Docket No. EL06-97-000 to September 15, 2006.
The extension is requested because of the complexity of the issues raised
by the Complainants and the intervening Labor Day holiday. This proceeding
involves a complaint by Wisconsin Public Service Corporation and some
of its affiliates (collectively "WPS") requesting the Commission
to direct Midwest ISO and PJM to institute joint unit commitment and
dispatch of their respective systems and undertake certain other steps
as part of their joint and common market effort.
- 08.24.2006
Docket
No. EL06-90-000 (PDF)
On August 24, 2006, PJM filed in Docket No. EL06-90-000 an answer to
the Complaint of PPL EnergyPlus, LLC, et al.
- 08.23.2006
Docket
No. ER06-1396-000 (PDF)
On August 23, 2006, PJM submitted to the Commission an executed interim
interconnection service agreement ("Interim ISA") among PJM,
FirstEnergy Nuclear Operating Company, Duquesne Light Company and American
Transmission Systems Incorporated. PJM submitted this Interim ISA as
the parties required non-conforming changes to the form of Interim ISA
in Attachment O-1 of the PJM Tariff to accommodate this interconnection.
PJM requested waiver of the Commission's 60-day notice requirement to
allow an effective date of August 15, 2006 for Original Service Agreement
No. 1537.
- 08.23.2006
EL06-94-000
(PDF)
On August 23, 2006, in Docket No. EL06-94-000, PJM filed an Answer to
the Complaint of The Borough of Chambersburg, Pennsylvania and The Town
of Front Royal, Virginia.
- 08.16.2006
ER06-1357-000
(PDF)
On August 16, 2006 PJM Interconnection, L.L.C. filed with the Commission
a Motion to Intervene in the matter of Docket ER06-1357-000.
- 08.15.2006
ER05-1410-000,
EL05-148-000 (PDF)
On August 15, 2006, PJM filed an answer opposing the late intervention
of MaGrann Associates in Docket Nos. ER05-1410-000 and EL05-148-000.
- 08.15.2006
Docket
No. ER06-1310-000 (PDF)
On July 31, 2006, PJM Interconnection, L.L.C. submitted for filing with
FERC an agreement for network integration transmission service between
PJM and American Electric Power Service Corporation, et al., designated
as Original Service Agreement No. 1536. On August 14, 2006, PJM amended
its July 31 filing and submitted Substitute Original Service Agreement
No. 1536. PJM requested that the service agreement be made effective
July 1, 2006, as it had in the July 31 filing.
- 08.15.2006
Docket
No. EL06-97-000 (PDF)
On August 15, 2006, in Docket No. EL06-97-000, Wisconsin Public Service
Corporation, Upper Peninsula Power Company, WPS Energy Services, Inc.
and its subsidiary WPS Power Development, LLC, collectively "WPS"
filed a complaint pursuant to Section 206 of the Federal Power Act and
the Commission's May 16, 2006 order in Docket Nos. EL06-20-000, et al.
against MISO and PJM.
- 08.14.2006
Docket
No. ER06-826-000 (PDF)
On August 14, 2006, in accordance with the Commission's July 14, 2006
Order, PJM submitted a compliance filing in Docket No. ER06-826.
- 08.14.2006
Docket
No. EL05-121-000 (PDF)
On August 14, 2006, PJM Interconnection, L.L.C. submitted for filing
with the FERC it's Brief on Exceptions in Docket No. EL05-121-000.
- 08.11.2006
Docket
No. ER06-xxx-000 (PDF)
On August 11, 2006, PJM filed with FERC revisions to the chart in Schedule
2 of the PJM Tariff: (i) to incorporate revised or new revenue requirements
of FPL Energy Marcus Hook, L.P., Old Dominion Electric Cooperative ,
UGI Development Company, and Allegheny Energy Supply, Company, L.L.C.,
for providing cost-based Reactive Support and Voltage Control from Generation
Sources Service in the PJM region; and (ii) to delete the Reactive Power
revenue requirement of ISG Sparrows Point, Inc. because the generator
associated with that revenue requirement is operating behind the meter.
- 08.08.2006
Docket
Nos. RM05-25-000 and RM05-17-000 (PDF)
On August 7, 2006, PJM Interconnection, LLC, submitted Comments regarding
the Order No. 888 OATT Reform Notice of Proposed Rulemaking (NOPR) in
Docket Nos. RM05-25 and RM05-17.
- 08.07.2006
Docket
No. ER06-199-000 (PDF)
On August 7, 2006, in compliance with the FERC's July 7 order in Docket
No. ER06-199, PJM filed revised PJM Tariff sheets revising certain of
its small generation facility interconnection provisions.
- 08.04.2006
Docket
No. ER06-1177-000 (PDF)
On August 4, 2006 PJM filed an answer to the protest of Indeck-Elwood,
L.L.C. in Docket No. ER06-1177-000 regarding PJM's proposed amendments
to Part IV of the PJM Tariff regarding the option to build and security
provisions.
- 08.03.2006
EL06-55-000
(PDF)
On August 3, 2006, in Docket No. EL06-55-000, PJM filed PJM Tariff and
Operating Agreement amendments that implement accounting for transmission
line losses on a marginal rather than an average basis. PJM also included
a proposal to allocate the surplus of funds resulting from this reform.
- 08.04.2006
Docket
No. ER06-1343-000 (PDF)
On August 3, 2006, PJM filed with FERC a Wholesale Market Participation
Agreement (Q44) executed by Masonic Villages of PA, PPL Electric Utilities
Corporation and PJM Interconnection, L.L.C. PJM is submitting this filing
because Masonic Villages of PA desires to conduct wholesale sales of
electric energy in the PJM markets from a generating facility connected
to PPL distribution facilities.
- 08.02.2006
ER05-1410-000,
EL05-148-000 (PDF)
On August 2, 2006, PJM filed an answer opposing the late intervention
of Conservation Services Group in Docket Nos. ER05-1410-000 and EL05-148-000.
Return
to Top |
Unsubscribe Instructions
This e-mail newsletter was sent to PJM members. If you do not wish to receive
the PJM Inside Lines newsletter in the future, please click here.
Customer Service
We are unable to respond to account inquiries sent in reply to this e-mail. To contact us by phone, please call our member hotline at 610.666.8980 or toll free 866.400.8980.
© 2006 PJM Interconnection. All rights reserved. |