PJM has extended a Maximum Generation Alert and Load Management Alert, originally issued for Oct. 13, to remain in effect through Oct. 14.

This alert does not require any action from customers.

PJM continues to proactively implement procedures to reliably serve increased electricity demand caused by unusually warm fall weather amid planned equipment outages required for maintenance and construction.

A PJM Capacity Advisory remains in place for Oct. 13–14, as well as a Maintenance Outage Recall for Oct. 14. An emergency order granted by the U.S. Dept. of Energy allows PJM to call on generators in excess of their operating permits as needed and to direct data centers and other Large Loads onto backup generation if necessary.

A Maximum Generation Alert notifies transmission and generation owners that system conditions will be tight. Those owners then determine if any equipment maintenance or testing may be deferred or canceled. By deferring such actions, units and transmission lines stay operational to serve demand. The alert also notifies neighboring grid operators that exports from PJM may be curtailed, a procedural step that allows them to plan accordingly.

PJM issues a Maximum Generation Alert at the same time as a Load Management Alert, which gives advance notice that such action may be declared, including Pre-Emergency and Emergency Demand Response.

On Oct. 13 and 14, PJM issued a Pre-Emergency Load Management Action to allow PJM to reliably serve the afternoon peak and evening net-load peak period when solar resources reduce to zero. Load Management includes Demand Response programs that pay customers in advance to reduce electricity use at PJM’s direction during stressed grid conditions. Additionally, PJM recalled non-firm sales to neighboring systems in coordination with their Balancing Authorities.

Issued up to five days in advance, a Capacity Advisory anticipates PJM actions such as:

  • Recalling or rescheduling of generation and/or transmission maintenance outages
  • Notifying neighboring grids to prepare for decreased imports from PJM
  • Alerting PJM Members to update their information about generator availability, fuel supply concerns, environmental constraints and more

Managing Planned Shoulder Season Outages

PJM is currently in planned maintenance season. Typically, both transmission and generation facilities are taken out of service to perform maintenance and construction from mid-September through early December, so they are fully available to serve loads during peak winter periods. 

PJM has recalled or canceled transmission and generation outages to the extent possible. This includes recall of all active generation maintenance outage tickets in the region PJM serves effective noon on Oct. 14. Generation outages were at approximately 61,000 MW Tuesday, in addition to key transmission outages to allow for both maintenance and major transmission construction projects.

“Unseasonable weather patterns are providing fewer days to perform important maintenance or construction on the generation and transmission equipment serving our footprint,” said Mike Bryson, PJM Sr. Vice President – System Operations. “This is the new reality that grid operators are facing, but PJM is confident that our procedures, along with the DOE orders, gives us additional tools to maintain our reserve margins and allow us to operate reliably.”

The emergency procedures took place as above-normal temperatures are forecast across much of the PJM region through Oct. 14, with hotter conditions continuing South and West.

As of 2 p.m. Tuesday, forecasted electricity demand, or load, for the affected period is:

Tuesday – 112,447 MW

Wednesday – 113,312 MW

These numbers are subject to change and will be updated.

Additional Actions

PJM requested and received a combined emergency order, effective from Oct. 13–16, from the U.S. Department of Energy. The 202c order grants PJM operators additional flexibility to respond to changing system conditions by:

  • Providing temporary relief from environmental permit restrictions for generating units
  • Authorizing PJM to direct data centers and other Large Load customers to switch to backup generation resources, if necessary.

The DOE has issued similar orders during extreme conditions in 2026. PJM has not had to make use of Large Load backup generation to date.

Additional emergency procedures may be necessary pending system conditions.