PJM Begins Accepting Expedited Interconnection Track Requests

406

PJM began accepting applications July 31 for large generation projects that are backed by a primary siting authority and can commence operation within three years.

The Expedited Interconnection Track (EIT) is a temporary, standalone process designed to address the urgent need for more capacity resources. It was accepted by the Federal Energy Regulatory Commission on June 9.

Through the EIT, PJM will consider up to 10 interconnection requests per calendar year in 2026 and 2027 for large new or uprated capacity resources. To qualify, these resources must have, among other requirements, a commitment from a relevant state authority to help expedite siting – one of the hurdles many projects face after receiving PJM’s permission to connect with the grid.

A project must also offer at least 250 MW of unforced capacity, the amount credited for reliability purposes.

PJM expects the projects to execute a Generation Interconnection Agreement within 10 months of submission. Proposals will be accepted on a rolling basis until the limit is reached for that calendar year. The EIT process will sunset at the end of 2027.

The EIT is one element of a multifaceted approach to address supply/demand challenges in the PJM region resulting from significant growth in the demand for electricity, particularly from data centers and other so-called “Large Load” customers.

The various elements were outlined in a Jan. 16 letter (PDF) from the Board of Managers implementing a Critical Issue Fast Path process addressing the challenges associated with connecting Large Loads. Other initiatives include:

The Board laid out its decision on how to pursue Reliability Backstop Procurement and Interim Resource Adequacy Service in a July 27 letter (PDF).